Thai Binh 2 Thermal Power Plant Project 2x600MW



  • SOIL IMPROVEMENT WORK ITEM:
    Information:
    - Total area:
       Main power island: 15 ha
       Coal storage yard: 10ha
       Switch yard and administration building: 4.6 ha
    - Depth of PVDs installation: ~ 30m
    - Design vacuum pressure: > 70kPa
    - Depth of clay sealing wall: 17m
    TECHICAL SPECIFICATIONS
    - Bearing capacity : 20kPa - 40kPa
    - Residual settlement affet 10 years: < 20cm
    PERORMANCE OF SOIL IMPROVEMENT WORK:
    - Total time of vacuum system operation : ~10 days
    - Total settlement due to SIW: ~8cm
    - Degree of consolidation: > 95.5%
    Pictures of the construction soil improvement work.